NEW CONSTRUCTION CHECKLIST
 


This checklist has been complied to address most common problems encountered during the
installation of the Protect-All flooring in a commercial kitchen application. The most important
item is #6. It is vital that all drains be installed properly and that the concrete substrate is
smooth and properly sloped to drains. This is the responsibility of the customer project
manager or the construction company company.

Please review this list carefully and if you have any question, please call (919) 852-5279.
R. Dale Brock, Director of Operations

 

A signed form MUST be returned to B & H Commercial Services before the flooring installation can be scheduled.  You can download this form by clicking here.

SUBSTRATE FLOOR CONDITION:

1) CONCRETE SLAB MUST BE FULLY CURED, DRY AND MEET HYDROSTATIC MOISTURE CONDITIONS OF NO MORE THAN 3 POUNDS PER 1000 SQUARE FEET.

2) SUBSTRATE SHOULD BE GRADED (SLOPED) TO DRAINS AS NECESSARY TO MEET LOCAL HEALTH DEPARTMENT REQUIREMENTS.

3) CONCRETE FLOORS MUST BE LEVEL EXCEPT FOR DRAIN SLOPE AS RREQUIRED AND CLEARED OF DEBRIS AND EQUIPMENT.

4) THE USE OF MUD SET IS NOT RECOMMENDED. CONTACT B & H DIRECTLY FOR REQUIREMENTS AND APPROVALS IF MUDSET MUST BE USED.

INSTALLATION AREA:

1) MUST BE FULLY ENCLOSED AND WATER TIGHT.

2) ROOF AND WALLS MUST BE FULLY CONSTRUCTED AND SECURED.

DRAINS:

1) MUST BE CLEARLY VISIBLE, ACCESSIBLE AND FREE OF DEBRIS.

2) ALL SQUARE, ROUND AND TROUGH FLOOR DRAINS ARE TO BE INSTALLED 1/8” ABOVE SUBSTRATE LEVEL TO ACCOMMODATE FLOORING MATERIAL.

3) ARE TO BE INSTALLED HORIZONTAL TO SUBSTRATE HEIGHT IE: DRAINS SHOULD NOT BE INSTALLED AT AN ANGLE TO FLOOR SURFACE.

4) ARE TO BE IN WORKING ORDER AND DRAIN PROPERLY.

5) ALL DRAIN COVERS AND ACCOMPANYING HARDWARE MUST BE PRESENT AND UNDAMAGED. WALL CONDITIONS:

1) WALLS MUST BE COMPLETELY ENCLOSED WITH SHEETROCK FULLY INSTALLED EXTENDING TO SUBSTRATELEVEL.

2) FRP MUST BE FULLY INSTALLED AND EXTEND TO THE SUBSTRATE LEVEL.

3) CERAMIC TILE WALLS MUST BE COMPLETELY INSTALLED AND EXTEND TO THE SUBSTRATE LEVEL.

4) STAINLESS WALLS ARE TO BE COMPLETELY SECURED.

DOORS:

1) DOOR FRAMES MUST BE COMPLETELY INSTALLED

2) DOORS IN AREAS OF NEW FLOOR INSTALLATION SHOULD BE INSTALLED TO ALLOW FOR A MINIMUM OF ½” TO ACCOMMODATE FLOORING MATERIAL AND STAINLESS TRANSITION.

COOLERS & FREEZERS: (IF SPECIFIED FOR INSTALLATION)

1) MUST BE FULLY ASSEMBLED AND INSTALLED.

2) MUST BE WATER TIGHT AND COMPLETELY SEALED.

3) CONCRETE FLOOR SURFACES MUST MEET MINIMUM REQUIREMENTS ABOVE FOR SUBSTRATE CONDITIONS.

4) SHOULD NOT BE OPERATED 48 HOURS PRIOR TO OR IMMEDIATELY AFTER NEW FLOOR INSTALLATION.

BAR AREAS: (IF SPECIFIED FOR INSTALLATION)

1) BARS SHOULD BE COMPLETELY INSTALLED PRIOR TO FLOORING INSTALLATION.

PLUMBING:

1) PLUMBING INSTALLATION MUST BE COMPLETED PRIOR TO THE ARRIVAL OF THE FLOORING CREW.

2) PLUMBING AND EQUIPMENT PIPE CONNECTIONS ARE TO BE DISCONNECTED AND CAPPED PRIOR TO THE COMMENCEMENT OF FLOORING INSTALLATION.

GAS LINES:

1) ARE TO BE INSTALLED 9” ABOVE SUBSTRATE LEVEL.

2) ARE NOT TO BE ANCHORED TO FLOORING AFTER FLOORING COMPLETION OR FLOOR WARRANTY MAY BE VOIDED.

WASTE REMOVAL:

1) CUSTOMER MUST PROVIDE ADEQUATE WASTE REMOVAL CONTAINERS (DUMPSTERS) FOR FLOORING MATERIALS AND DEBRIS TO BE REMOVED FROM THE JOB SITE.

WATER ACCESS:

1) HOT (IF AVAILABLE) AND COLD WATER ACCESS WITH STANDARD WATER HOSE CONNECTIONS.

POWER ACCESS:
1) ELECTRICAL POWER DEDICATED TO FLOORING CREW AND AVAILABLE DURING FLOORING INSTALLATION WITH A MINIMUM OF 3 SEPARATE 20 AMP ELECTRICAL OUTLETS REQUIRED.

2) A POWER GENERATOR OR GENERATORS MEETING THE ABOVE REQUIREMENTS MUST BE PROVIDED BY THE
CUSTOMER IF ADEQUATE BUILDING POWER IS NOT AVAILABLE.

SITE ACCESS:

1) CUSTOMER WILL INSURE B & H INSTALLATION CREW HAS UNRESTRICTED ACCESS TO THE JOBSITE AS SCHEDULED.

2) CUSTOMER MUST NOTIFY B & H A MINIMUM OF 48 HOURS IN ADVANCE SHOULD THERE BE SITE ACCESS LIMITATIONS.

MATERIAL DELIVERY:

1) BASED ON START DATE OF INSTALLATION, CUSTOMER MAY BE ASKED TO RECEIVE DELIVERY OF AND UNLOAD ALL FLOORING MATERIALS INCLUDING:
a) PROTECT-ALL VINYL FLOORING MATERIAL & ADHESIVES.
b) STAINLESS STEEL FIXTURES AND ACCESSORIES.
(A weekend starting date may require a coordinated effort between customer and B & H for material delivery).

STORAGE:

1) PROTECT-ALL FLOORING MATERIAL IS TO BE LAID FLAT WHILE STORED.

2) PROTECT-ALL FLOORING MATERIAL, STAINLESS FIXTURES, ADHESIVES AND ACCESSORIES ARE TO BE STORED IN A DRY AND SECURE LOCATION.

3) PRODUCT LOSS OR DAMAGE IS THE RESPONSIBILITY OF THE CUSTOMER.

CONTACT LIST:

1) CUSTOMER WILL PROVIDE B & H WITH A WRITTEN CONTACT LIST AND POINT OF CONTACT (POC) AUTHORIZED TO SIGN ANY CHANGE ORDERS A MINIMUM OF 2 WEEKS PRIOR TO PROJECT START.

2) CONTACT LIST WILL INCLUDE:
a) GENERAL CONTRACTOR PHONES & ADDRESS
b) PROJECT MANAGER (INCLUDING CELL PHONE #)
c) JOB SUPERINTENDENT (INCLUDING CELL PHONE #) ASSESSMENTS:

1) ASSESSMENTS, IF INCURRED, ARE BILLED AT A RATE OF $50.00 PER HOUR PER MAN TO A MAXIMUM OF $1000.00 PER DAY.

2) ASSESSMENTS MAY BE INCURRED FOR THE FOLLOWING:
a) CUSTOMER HAS NOT MET CONSTRUCTION CHECKLIST ITEMS PRIOR TO ARRIVAL OF THE FLOORING CREW CAUSING A DELAY IN JOB START.
b) CONSTRUCTION PROJECT IS BEHIND SCHEDULE AND CUSTOMER DOES NOT NOTIFY B & H OF NEED TO RESCHEDULE A MINIMUM OF 6 DAYS PRIOR TO ARRIVAL OF FLOORING CREW.
c) HEAVY RAINS, WINDS OR NATURAL DISASTERS CAUSE FLOODING OR STRUCTURAL DAMAGE TO THE BUILDING CAUSING B & H TO BE UNABLE TO WORK OR COMPLETE THE PROJECT ON TIME.

SPECIAL CONSIDERATIONS:
B & H IS TO BE ADVISED IN WRITING OF SPECIAL CONSIDERATIONS OR UNUSUAL
REQUIREMENTS ON THE JOBSITE PRIOR TO ACCEPTANCE OF PROPOSAL (QUOTATION) SUCH AS:
1) LABOR UNION CONCERNS
2) FREIGHT DELIVERY& UNLOADING RESTRICTIONS
3) BUILDING SECURITY
4) PARKING RESTRICTIONS
5) SITE ACCESS RESTRICTIONS
(FAILURE TO DISCLOSE ANY OF THE ABOVE SPECIAL CONSIDERATIONS PRIOR TO ACCEPTANCE OF PROPOSAL BY BOTHPARTIES WILL SUBJECT PROPOSAL TO BE NULL AND VOID REQUIRING A NEW PROPOSAL BE SUBMITTED FORACCEPTANCE).

ASDFASDF
Please Note: The General Contractor Project Superintendant Is Repsonsible For Pressure Washing The Floor Immediately Prior To Kitchen Equipment Delivery. Construction Grime And Dirt Should Not To Be Present When Operator Takes Delivery Of Location.